Motorway link Šmarje - Sap
Client / investor: DARS
Project category: Projects
Project time span: July 2016 - October 017
CGP, d.d. was selected as the most favourable provider at the public tender published by DARS d.d.
The structure is considered to be a complex construction and contains numerous sub-assemblies.
MW link Šmarje Sap – Ljubljana with the length of 540.00m and MW link Ljubljana – Šmarje Sap with the length of 430m, reconstruction and new construction of national roads with a total length of 1020.00 m, new construction of local roads with the length of 220.00m, new construction of sidewalks with the length of 870.00m, reconstruction of the existing OVERPASS on the motorway Malence-Šmarje Sap, reconstruction of the existing OVERPASS on the railway line Ljubljana-Novo mesto.
Rain water system, sewage system, water supply system, electrical installations and public lighting, telecommunication lines.